Lesson 6: Budget Estimation and Project Planning
Date: September 11, 2025
Session Time: 8:00am-12:00pm EST
Duration: 4 hours (including 15-minute exercise)
Key Learning Objective
Estimating project costs accurately and creating comprehensive project plans through systematic analysis and planning techniques.
Lesson Overview
This session teaches fundamental project management skills including cost estimation, timeline development, and risk assessment for construction projects.
Main Activities (3 hours 45 minutes)
- Cost estimation methods and best practices
- Project planning frameworks and tools
- Risk identification and mitigation strategies
- Timeline development and critical path analysis
- Budget tracking and management systems
15-Minute Exercise: Mini Project Budget
Exercise Description
Create a detailed budget estimate for a small deck component (e.g., 10' x 10' section) using systematic cost estimation techniques and create a simple project timeline.
Materials Needed
- Calculator
- Spreadsheet software or paper
- Previous materials research
- Notebook for calculations
- Timer or clock
Exercise Steps (15 minutes)
- Scope Definition (2 minutes)
- Define the specific component (e.g., "10' x 10' deck section")
- List all materials needed (from previous research)
- Identify any tools or equipment required
-
Note any special requirements or constraints
-
Cost Calculation (8 minutes)
- Calculate material costs using your research data
- Estimate labor hours (if applicable)
- Add 10% contingency for unexpected costs
- Calculate total estimated cost
-
Break down costs by category (materials, labor, tools, etc.)
-
Timeline Creation (3 minutes)
- Create a simple timeline with 3-5 major steps
- Estimate duration for each step
- Identify any dependencies between steps
-
Note any critical path items
-
Risk Assessment (2 minutes)
- Identify 2-3 potential risks or challenges
- Note potential cost impacts
- Suggest one mitigation strategy for each risk
Deliverable
- Detailed cost breakdown by category
- Total estimated cost with contingency
- Simple project timeline with steps and durations
- Risk assessment with mitigation strategies
Success Criteria
- Cost estimates are based on research data
- Timeline is realistic and logical
- Contingency is included appropriately
- Risks are identified with practical mitigation strategies
Integration with Overall Project
This exercise develops the budgeting and planning skills essential for the full project and establishes the framework for tracking costs and progress throughout construction.
Previous Session: Lesson 5: Materials Research
Next Session: Lesson 7: Design Finalization