FRS 16 Hull Build: Project Plan
Project: Scoughxxuene 2.0 Hull Build Student: John Hurff Semester: Fall 2026 Build Window: August 6 – December 10, 2026 Shop Day: Thursday, 8:00 AM – 12:00 PM
Phase Milestones
| Phase | Sessions | Thursdays | Target Completion | Status |
|---|---|---|---|---|
| 1: Setup & Planning | 1–3 | Aug 6, 13, 20 | August 20, 2026 | Pending |
| 2: Stitching | 4–6 | Aug 27 – Sep 10 | September 10, 2026 | Pending |
| 3: Framing & Epoxy Seams | 7–9 | Sep 17 – Oct 1 | October 1, 2026 | Pending |
| 4: Epoxy Sealing & Fiberglass | 10–12 | Oct 8–22 | October 22, 2026 | Pending |
| 5: Custom Build-Out | 13–15 | Oct 29 – Nov 12 | November 12, 2026 | Pending |
| 6: Finishing | 16–18 | Nov 19 – Dec 10 | December 10, 2026 | Pending |
| Final Report | — | — | December 10, 2026 | Pending |
Class Schedule
18 shop sessions on Thursdays, 8:00 AM – 12:00 PM. Thanksgiving week (November 26) is skipped.
Quick Reference
| Session | Date | Phase | Focus |
|---|---|---|---|
| 1 | Thu, Aug 6 | Phase 1 | Course Kickoff & Safety Orientation |
| 2 | Thu, Aug 13 | Phase 1 | Kit Inventory & Verification |
| 3 | Thu, Aug 20 | Phase 1 | Customization Design & Material Planning ✓ |
| 4 | Thu, Aug 27 | Phase 2 | Hull Panel Dry Fit |
| 5 | Thu, Sep 3 | Phase 2 | Stitching — Hull Bottom & Sides |
| 6 | Thu, Sep 10 | Phase 2 | Stitching — Transom, Bow & Completion ✓ |
| 7 | Thu, Sep 17 | Phase 3 | Frame & Bulkhead Installation |
| 8 | Thu, Sep 24 | Phase 3 | Thickened Epoxy — Interior Seams |
| 9 | Thu, Oct 1 | Phase 3 | Thickened Epoxy — Exterior Seams & Keel ✓ |
| 10 | Thu, Oct 8 | Phase 4 | Epoxy Seal — All Interior Surfaces |
| 11 | Thu, Oct 15 | Phase 4 | Fiberglass Cloth — Interior |
| 12 | Thu, Oct 22 | Phase 4 | Fiberglass Cloth — Exterior & Hull Bottom ✓ |
| 13 | Thu, Oct 29 | Phase 5 | Storage Compartments & Livewell Rough-In |
| 14 | Thu, Nov 5 | Phase 5 | Casting Deck & Flooring |
| 15 | Thu, Nov 12 | Phase 5 | Rod Holders, Accessory Mounts & Hardware ✓ |
| 16 | Thu, Nov 19 | Phase 6 | Sanding, Fairing & Paint Prep |
| — | Thu, Nov 26 | — | THANKSGIVING BREAK — No Session |
| 17 | Thu, Dec 3 | Phase 6 | Primer Application |
| 18 | Thu, Dec 10 | Phase 6 | Final Paint (USA Theme) & Hull Completion ✓ |
✓ = Phase checkpoint session
Week-by-Week Schedule
Session 1 — Thursday, August 6
Phase 1: Setup & Planning Focus: Course Kickoff & Safety Orientation
Accomplish this session:
-
[ ] Review course overview, SMART goal, and semester schedule with Jimmy
-
[ ] Conduct full shop safety orientation — PPE, epoxy and solvent handling, power tool safety, ventilation
-
[ ] Set up workbenches and tool stations in the garage
-
[ ] Organize chemical storage (epoxy, solvents, primers)
-
[ ] Walk through the FRS 16 build plans together — identify all major sections
-
[ ] Complete and sign shop safety checklist
-
[ ] Document workspace setup with photos
-
[ ] Write Journal Entry 1
Session 2 — Thursday, August 13
Phase 1: Setup & Planning Focus: Kit Inventory & Verification
Accomplish this session:
-
[ ] Unpack all CNC-cut panels and lay them out
-
[ ] Cross-reference every panel against the build plans and parts list
-
[ ] Label each panel with chalk or painter's tape (panel name and orientation)
-
[ ] Photograph every panel (guest photo catalog task)
-
[ ] Inventory all supplemental materials — foam, hardware, plans, HIN documentation
-
[ ] Note and document any missing or damaged components
-
[ ] Write Journal Entry 2
By end of session: Every kit component identified, labeled, and photographed.
Session 3 — Thursday, August 20
Phase 1: Setup & Planning Focus: Customization Design & Material Planning Phase 1 Checkpoint
Accomplish this session:
-
[ ] Finalize customization design — storage compartment locations, livewell size and placement, casting deck dimensions, rod holder positions
-
[ ] Produce interior layout design sketch with all custom features marked
-
[ ] Research and select USA-made materials and hardware for all categories
-
[ ] Complete full material procurement list with sources and USA-made designations
-
[ ] Place orders for all long-lead materials — epoxy, fiberglass cloth, foam (if not in kit), paint, rod holders, livewell hardware
-
[ ] Verify all materials will arrive before Session 5 (stitching begins)
-
[ ] Write Journal Entry 3
Phase 1 Complete when: All panels labeled and inventoried; design sketch finalized; all materials ordered or confirmed on hand.
Session 4 — Thursday, August 27
Phase 2: Stitching Focus: Hull Panel Dry Fit
Accomplish this session:
-
[ ] Set up building supports and sawhorses on the shop floor
-
[ ] Begin fitting hull bottom panels — no stitching yet, dry fit only
-
[ ] Fit port and starboard side panels against the hull bottom
-
[ ] Check panel alignment and hull symmetry from bow to stern
-
[ ] Verify rocker (the curve of the hull bottom from bow to stern)
-
[ ] Mark all stitch points along every seam — every 6 to 8 inches
-
[ ] Write Journal Entry 4
By end of session: All panels dry-fit in correct position; stitch points marked on all seams.
Session 5 — Thursday, September 3
Phase 2: Stitching Focus: Stitching — Hull Bottom & Sides
Accomplish this session:
-
[ ] Drill stitch holes at all marked points along hull bottom and side seams
-
[ ] Stitch hull bottom panels together at centerline with zip ties
-
[ ] Stitch port side panel to hull bottom
-
[ ] Stitch starboard side panel to hull bottom
-
[ ] Check and adjust hull shape as stitching progresses — tension zip ties to achieve correct form
-
[ ] Write Journal Entry 5
By end of session: Hull bottom stitched at centerline; both sides stitched to bottom; hull beginning to take shape.
Session 6 — Thursday, September 10
Phase 2: Stitching Focus: Stitching — Transom, Bow & Completion Phase 2 Checkpoint
Accomplish this session:
-
[ ] Stitch transom panel to hull bottom and sides
-
[ ] Stitch bow panel into position
-
[ ] Stitch any remaining structural panels — spray rails, chine panels per plans
-
[ ] Verify symmetry: measure beam width at bow, mid-ship, and stern — port and starboard must match
-
[ ] Record beam measurements in journal
-
[ ] Trim all zip tie tails flush
-
[ ] Write Journal Entry 6
Phase 2 Complete when: Hull fully stitched; all panels in final position; beam symmetric at all three measurement stations.
Session 7 — Thursday, September 17
Phase 3: Framing & Epoxy Seams Focus: Frame & Bulkhead Installation
Accomplish this session:
-
[ ] Review frame locations in build plans before cutting or fitting anything
-
[ ] Fit Frame 1 — trim as needed for a clean fit against hull panels
-
[ ] Check Frame 1 for plumb (vertical) and correct position fore/aft
-
[ ] Temporarily secure Frame 1 with clamps or zip ties
-
[ ] Repeat for all remaining frames and bulkheads
-
[ ] Verify frame spacing matches plans after all frames are in
-
[ ] Mark fillet locations at all frame-to-hull joints
-
[ ] Write Journal Entry 7
By end of session: All frames and bulkheads fitted, positioned, and temporarily secured.
Session 8 — Thursday, September 24
Phase 3: Framing & Epoxy Seams Focus: Thickened Epoxy — Interior Seams & Fillets
Accomplish this session:
-
[ ] Mix first batch of thickened epoxy — record ratio, temperature, and pot life in log
-
[ ] Apply epoxy fillets to interior panel seams working systematically bow to stern
-
[ ] Apply epoxy fillets at all frame-to-hull-bottom joints
-
[ ] Apply epoxy fillets at all frame-to-hull-side joints
-
[ ] Smooth all fillets to a consistent radius using a radius tool or gloved finger
-
[ ] Allow to cure per manufacturer specifications before disturbing
-
[ ] Log all epoxy batches mixed this session
-
[ ] Write Journal Entry 8
By end of session: All interior panel seams and frame joints filleted.
Session 9 — Thursday, October 1
Phase 3: Framing & Epoxy Seams Focus: Thickened Epoxy — Exterior Seams & Keel Phase 3 Checkpoint
Accomplish this session:
-
[ ] Access or flip hull to work on exterior seams
-
[ ] Mix thickened epoxy and apply fillets to all exterior chine seams (where bottom meets sides)
-
[ ] Apply keel fillet — a continuous, generous bead running the full length of the hull bottom centerline
-
[ ] Feather and smooth all exterior fillets
-
[ ] Inspect all interior fillets from Session 8 — fill any voids or thin spots
-
[ ] Log all epoxy batches mixed this session
-
[ ] Write Journal Entry 9
Phase 3 Complete when: All interior and exterior seams filleted; all frame joints bonded; no voids or gaps; keel fillet full length.
Session 10 — Thursday, October 8
Phase 4: Epoxy Sealing & Fiberglass Focus: Epoxy Seal — All Interior Surfaces
Accomplish this session:
-
[ ] Mix neat (unfilled) epoxy per manufacturer instructions
-
[ ] Apply first seal coat to all interior surfaces — use rollers on flat areas, brushes in corners and tight spots
-
[ ] Work section by section to avoid missing any areas
-
[ ] Apply second coat before first coat fully cures (green stage) for maximum penetration
-
[ ] Inspect for any dry spots or fisheyes; re-coat as needed
-
[ ] Pre-cut fiberglass cloth panels for Session 11 while epoxy cures
-
[ ] Write Journal Entry 10
By end of session: All interior surfaces sealed with minimum two coats; fiberglass cloth pre-cut for interior application.
Session 11 — Thursday, October 15
Phase 4: Epoxy Sealing & Fiberglass Focus: Fiberglass Cloth — Interior Application
Accomplish this session:
-
[ ] Dry-fit all pre-cut interior fiberglass cloth pieces before mixing any epoxy
-
[ ] Wet out and apply fiberglass cloth to hull bottom interior
-
[ ] Wet out and apply fiberglass cloth to bilge and keel area
-
[ ] Wet out and apply fiberglass cloth to transom interior
-
[ ] Roll out air bubbles from each section — glass should be fully translucent when properly wetted
-
[ ] Trim excess cloth at edges while still wet
-
[ ] Write Journal Entry 11
By end of session: All required interior areas glassed; no dry spots (white areas) visible in cured layup.
Session 12 — Thursday, October 22
Phase 4: Epoxy Sealing & Fiberglass Focus: Fiberglass Cloth — Exterior & Hull Bottom Phase 4 Checkpoint
Accomplish this session:
-
[ ] Inspect and lightly sand interior glass work from Session 11 — knock down any high spots or ridges
-
[ ] Apply fiberglass cloth to hull bottom exterior — full coverage from chine to chine
-
[ ] Apply fiberglass tape over all exterior chine seams (both port and starboard)
-
[ ] Apply fiberglass cloth to transom exterior
-
[ ] Allow full cure before Phase 5 begins
-
[ ] Sand any rough glass edges once cured
-
[ ] Write Journal Entry 12
Phase 4 Complete when: All interior and exterior areas glassed; no dry spots; cured glass is solid and firmly bonded; hull is structurally complete.
Session 13 — Thursday, October 29
Phase 5: Custom Build-Out Focus: Storage Compartments & Livewell Rough-In
Accomplish this session:
-
[ ] Transfer interior layout design sketch to the actual hull — mark all compartment walls and livewell location with pencil or chalk
-
[ ] Cut interior divider walls for storage compartments to fit
-
[ ] Dry-fit all dividers; trim as needed
-
[ ] Epoxy-bond storage compartment dividers into position
-
[ ] Cut livewell opening to planned dimensions
-
[ ] Fit livewell liner or box into opening
-
[ ] Mark livewell drain and supply plumbing locations
-
[ ] Apply epoxy seal coat to all new wood surfaces in storage and livewell areas
-
[ ] Write Journal Entry 13
By end of session: Storage compartment structures installed; livewell roughed in with liner fitted and plumbing locations marked.
Session 14 — Thursday, November 5
Phase 5: Custom Build-Out Focus: Casting Deck & Flooring
Accomplish this session:
-
[ ] Cut casting deck panel(s) to fit the bow section — work incrementally, test-fitting often
-
[ ] Install deck support cleats along hull sides and forward frame
-
[ ] Dry-fit casting deck; verify fit and verify it sits level
-
[ ] Epoxy-bond casting deck into final position
-
[ ] Apply fiberglass cloth over casting deck surface for durability and sealing
-
[ ] Install any other deck flooring sections per design
-
[ ] Apply epoxy seal to all new wood
-
[ ] Write Journal Entry 14
By end of session: Casting deck installed, bonded, and glassed; all flooring sections complete.
Session 15 — Thursday, November 12
Phase 5: Custom Build-Out Focus: Rod Holders, Accessory Mounts & Hardware Phase 5 Checkpoint
Accomplish this session:
-
[ ] Mark all rod holder positions on hull sides and gunwales
-
[ ] Drill rod holder holes; install backing plates with wood doublers behind each
-
[ ] Install rod holder tubes and secure
-
[ ] Fabricate and install Power-Pole mounting bracket at transom — reinforce backing
-
[ ] Install trolling motor bow mount backer plate at bow
-
[ ] Mark jack plate mounting location on transom; apply wood doubler and glass reinforcement
-
[ ] Verify all USA-made hardware is on hand; document sourcing for each item
-
[ ] Write Journal Entry 15
Phase 5 Complete when: All storage, livewell, casting deck, rod holders, and accessory mount locations are installed, reinforced, and sealed.
Session 16 — Thursday, November 19
Phase 6: Finishing Focus: Sanding, Fairing & Paint Prep
Accomplish this session:
-
[ ] Inspect the full hull exterior — look at low angle against the light to spot high spots, ridges, and low areas
-
[ ] Apply epoxy fairing compound to any voids or low spots; allow to cure
-
[ ] Block sand full hull exterior — 80-grit first pass to knock down high spots
-
[ ] Block sand — 120-grit second pass
-
[ ] Block sand — 180-grit final pass for paint-ready surface
-
[ ] Hand sand edges, corners, chines, and any areas block can't reach
-
[ ] Wash hull with clean water; allow to fully dry
-
[ ] Tape off transom area, hardware mounts, and any areas not to be primed
-
[ ] Write Journal Entry 16
By end of session: Hull fully sanded fair and ready for primer; no rough edges or ridges remaining.
— Thursday, November 26 — THANKSGIVING BREAK — No Session —
Session 17 — Thursday, December 3
Phase 6: Finishing Focus: Primer Application
Accomplish this session:
-
[ ] Mix marine primer per manufacturer instructions — confirm USA-made product
-
[ ] Apply primer to full hull exterior using roller; cut in corners and edges with brush
-
[ ] Maintain a wet edge to avoid lap marks
-
[ ] Allow first coat to flash to touch; apply second coat if time allows
-
[ ] Inspect primed surface under good lighting for any remaining low spots, pinholes, or runs
-
[ ] Apply spot fairing compound to any newly revealed defects; sand when dry
-
[ ] Write Journal Entry 17
By end of session: Full hull exterior primed with at least one complete coat; any final defects identified and addressed.
Session 18 — Thursday, December 10
Phase 6: Finishing Focus: Final Paint (USA Theme) & Hull Completion Phase 6 Checkpoint — Hull Complete
Accomplish this session:
-
[ ] Apply final topcoat — base color first (full hull)
-
[ ] Allow base to flash; mask color break lines for secondary USA theme colors
-
[ ] Apply red and white (or blue) accent colors per design
-
[ ] Apply non-skid additive to all walking surfaces — casting deck, flooring
-
[ ] Remove all masking tape carefully
-
[ ] Final inspection — touch up any runs, holidays, or color bleeds
-
[ ] Guest signatures on transom interior (permanent record of everyone who built this boat)
-
[ ] Complete full build photo documentation set — all angles, interior and exterior
-
[ ] Submit final report
-
[ ] Write Journal Entry 18
Hull is complete when: Fully painted in USA theme; all surfaces smooth or non-skid; all custom features installed; final report submitted.
Detailed Phase Plan
Phase 1: Setup & Planning (Sessions 1–3 | Aug 6–20)
Goal: Safe, organized workspace ready to build. All components verified. All customizations designed and materials ordered.
Tasks:
-
[ ] Complete shop safety orientation; sign safety checklist
-
[ ] Set up workbenches, tool stations, and chemical storage
-
[ ] Unpack all CNC panels and cross-reference against parts list
-
[ ] Label all panels (chalk or tape)
-
[ ] Photograph complete kit inventory
-
[ ] Finalize interior customization design sketch
-
[ ] Identify all USA-made materials and hardware
-
[ ] Complete material procurement list
-
[ ] Place orders for any long-lead materials (foam, epoxy, paint, hardware)
Success Criteria: All panels accounted for and labeled; customization plan complete and documented; all materials ordered or on hand.
Phase 2: Stitching (Sessions 4–6 | Aug 27–Sep 10)
Goal: All hull panels stitched into correct shape and geometry verified.
Tasks:
-
[ ] Set up building supports/forms on shop floor
-
[ ] Dry fit all hull panels and verify alignment
-
[ ] Mark all stitch points (every 6–8 inches)
-
[ ] Drill stitch holes along all seams
-
[ ] Stitch hull bottom centerline
-
[ ] Stitch port and starboard sides to hull bottom
-
[ ] Stitch transom into position
-
[ ] Stitch bow panel
-
[ ] Stitch any remaining structural panels (chines, spray rails)
-
[ ] Verify symmetry: measure beam at 3+ stations; verify equal measurements port/starboard
-
[ ] Trim all zip tie tails
Success Criteria: Hull holds its full shape; beam measurements symmetric at all stations; no visible panel misalignment.
Phase 3: Framing & Epoxy Seams (Sessions 7–9 | Sep 17–Oct 1)
Goal: All frames and bulkheads installed; all interior and exterior seams filleted with thickened epoxy.
Tasks:
-
[ ] Fit, trim, and install all frames and bulkheads per plans
-
[ ] Verify frame spacing and plumb
-
[ ] Mix and apply thickened epoxy fillets — all interior seams
-
[ ] Mix and apply thickened epoxy fillets — all frame-to-hull joints
-
[ ] Mix and apply thickened epoxy fillets — all exterior chine seams
-
[ ] Apply keel fillet (full length, generous radius)
-
[ ] Inspect all fillets for voids; touch up as needed
-
[ ] Log all epoxy mix batches (ratio, temperature, pot life)
Success Criteria: All seams have consistent, full-radius fillets. No voids or gaps. All frames are square and bonded.
Phase 4: Epoxy Sealing & Fiberglass (Sessions 10–12 | Oct 8–22)
Goal: All wood surfaces sealed; all structural areas reinforced with fiberglass cloth.
Tasks:
-
[ ] Apply 2-coat epoxy seal to all interior surfaces
-
[ ] Inspect for dry spots and re-coat as needed
-
[ ] Pre-cut all fiberglass cloth panels (interior and exterior)
-
[ ] Wet out and apply fiberglass cloth — hull bottom interior
-
[ ] Wet out and apply fiberglass cloth — bilge/keel area
-
[ ] Wet out and apply fiberglass cloth — transom interior
-
[ ] Wet out and apply fiberglass cloth — hull bottom exterior (full coverage)
-
[ ] Apply fiberglass tape — all exterior chine seams
-
[ ] Apply fiberglass cloth — transom exterior
-
[ ] Inspect all glass work: no dry spots, no major air inclusions
-
[ ] Sand any rough edges or high spots from cured glass
Success Criteria: All required areas glassed. Glass is fully wetted out with no dry sections. Cured glass is solid and firmly bonded.
Phase 5: Custom Build-Out (Sessions 13–15 | Oct 29–Nov 12)
Goal: All custom interior features built and installed; all accessory mount locations reinforced.
Tasks:
-
[ ] Transfer design sketch to hull — mark all compartment walls and livewell location
-
[ ] Cut and fit storage compartment dividers
-
[ ] Epoxy-bond all storage compartment structures
-
[ ] Cut livewell opening; fit and bond livewell liner
-
[ ] Mark livewell drain and supply locations
-
[ ] Epoxy seal all new wood in storage and livewell areas
-
[ ] Cut casting deck panels to fit
-
[ ] Install deck support cleats
-
[ ] Epoxy-bond and glass casting deck
-
[ ] Install all rod holder tubes at planned positions
-
[ ] Install rod holder backing plates with wood doublers
-
[ ] Fabricate and install Power-Pole mounting bracket (transom)
-
[ ] Install trolling motor backer at bow
-
[ ] Mark and reinforce jack plate mounting location
-
[ ] Document all USA-made hardware installed
Success Criteria: All custom features installed and epoxy-bonded. All accessory mount locations reinforced and ready. All new wood sealed.
Phase 6: Finishing (Sessions 16–18 | Nov 19–Dec 10)
Goal: Hull fully sanded, primed, and painted in USA theme. Complete, photo-documented.
Tasks:
-
[ ] Inspect full hull for bumps, voids, and surface defects
-
[ ] Apply fairing compound to any low spots; sand flush
-
[ ] Block sand full hull exterior: 80-grit → 120-grit → 180-grit
-
[ ] Hand sand edges, corners, and tight areas
-
[ ] Wash hull and allow to dry
-
[ ] Tape off non-paint areas
-
[ ] Apply marine primer — full hull exterior (USA-made)
-
[ ] Inspect primed surface; address any remaining defects
-
[ ] Apply final topcoat — base color
-
[ ] Mask for secondary colors; apply remaining USA theme colors
-
[ ] Apply non-skid additive to all walking surfaces
-
[ ] Remove masking; final inspection and touch-up
-
[ ] Complete build photo documentation set
-
[ ] Guest signatures on transom interior before final coat
Success Criteria: Hull is fair, evenly painted in USA theme colors. All surfaces smooth or properly non-skid. Build complete.
Material Procurement Plan
Kit (Already Purchased)
- Salt Boatworks FRS 16 Plywood Kit (CNC-cut panels, USCG foam, capacity placard, HIN)
- Source: Salt Boatworks — saltboatworks.com
- Purchased from: Adam Parchman, Founder
Additional Materials to Procure
| Item | Specification | Qty | USA-Made Target | Status |
|---|---|---|---|---|
| Marine epoxy | 2-part epoxy system, ~12 gallons | 1 set | Yes | To order |
| Fiberglass cloth, 6 oz | Woven, ~50 yards | 1 roll | Yes | To order |
| Fiberglass cloth, 10 oz | Woven, ~55 yards | 1 roll | Yes | To order |
| Fiberglass tape, 4" | Biaxial or woven | 1 roll | Yes | To order |
| Silica (cab-o-sil) | Thickening agent | 1 lb | Yes | To order |
| Wood flour | Thickening agent | 1 lb | Yes | To order |
| Expanding foam | USCG-compliant flotation, ~10 cu ft | Per kit | Yes | Check kit |
| Marine primer | Full hull, 2 coats | 1 gallon | Yes | To order |
| Marine topcoat paint | USA theme colors (red, white, blue) | 2–3 gallons | Yes | To order |
| Non-skid additive | For deck and casting surface | 1 lb | Yes | To order |
| Rod holders | Flush mount, stainless | 4–6 | Yes | To order |
| Livewell kit | Pump, aerator, drain | 1 set | Yes | To order |
| Power-Pole bracket | Transom mount | 1 | — | To order |
| Trolling motor bracket | Bow mount | 1 | Yes | To order |
| Jack plate | Motor setback | 1 | Yes | Spring 2027 |
| Marine electronics | Fish finder, GPS | TBD | Yes | Spring 2027 |
USA-Made Product Sourcing Policy
Where possible, all materials and hardware should be sourced from USA manufacturers. Document the country of manufacture for each major purchase. If a USA-made option is not available or practical, document why.
Schedule Risk Management
| Risk | Mitigation |
|---|---|
| Epoxy or material delivery delay | Order all materials by Session 2 (Aug 13) |
| Extended cure times in cool weather | Monitor garage temperature; use epoxy rated for lower temperatures if needed |
| Session cancellation (illness, weather) | Journal entry still required; adjust schedule to compress next session |
| Fitting issues requiring rework | Build 1 session of buffer into each phase; Phase 5 is most likely to need extra time |